Analysis and prospect on Waste to Energy for electricity generation conducted within Aba metropolis establishes a
knowledge that about 173.3million kg of waste per annum can effectively generate about 426.07GWhr to
883.32GWhr electricity per annum dependent on type of waste used for Waste to Energy plant. The project considers
different kind of wastes, and energy generated from them jointly, in order to develop a framework for sustainable
waste-to-energy power plant. The aim of this paper is to take advantage of poorly disposed waste on our streets
diverted to landfill and some wastes that are indiscriminately degraded by heating and turn it to techno-economic asset
of waste to energy plant( to produce electricity).The set objective is to analyze the quantity of waste and its type in
Aba city and turn it to” waste to energy” (electricity). The literature review examines briefly the efforts of different
researchers and technologies used for waste to energy plant. The method used for this work summarily review the
mathematical model for calculating gross electricity generated from waste and the research diagram for the proposed
waste to energy plant. The analysis and results from the methods used for calculating energy generated from waste
shows that much energy can be generated from the waste of low heating value. Besides the areas with greater
population produces more waste than areas with lesser population of people.
Index Terms
Analysis Prospect Waste To Energy.How to cite this article
- Published: May 31, 2022
- Volume/Issue: Volume 5, Issue 1
- Pages: 1-6
PDF preview
Other papers in IJIETS
Browse additional articles authored by one or more contributors to this paper.